Customer Relations & Learning Technologies
Clemson Residential Area Wireless Project

Goal: Our university requires a modern wireless network and an underlying network infrastructure capable of meeting increased capacity in order to satisfy student and faculty expectations, stay competitive, and encourage innovation.

Objectives: Successfully implement wireless connectivity within all Clemson Residence Halls on Campus through a well communicated, aggressive schedule of wireless access point installations, configurations and tests.

Scope:   At this time, the project will provide wireless connectivity within the residence halls. Outdoor or green space and all stairwells within the residence halls are not considered within the scope of this project.  Once complete, access to the wireless network will require 802.11AG/WPA2 Enterprise laptop compatibility.  Faculty, staff, and students with laptops that do not meet the 802.11AG/WPA2 Enterprise technical standards should access the internet through wired connectivity.

     Wireless Help Website               Wireless Project FAQ                 Project Milestones

Residential Area Wireless Install Schedule
Residence  Name  Start Date     Target Completion % Complete
     Thornhill Apartments  1/16/09 1/16/09 100%
Wireless Service Installations      
     Lightsey Bridge I Apts  2/2/09 2/9/09 100%
     Calhoun Courts Bldg Automation  1/30/09 2/4/09 100%
     Calhoun Courts Wireless  3/30/09 4/13/09 100%
     Lightsey Bridge II Apts - Bldg Automation  2/17/09 2/18/09 100%
     Lightsey Bridge II Apts   2/13/09 3/6/09 100%
     ManningBldg Automation  3/6/09 4/1/09 100%
     Manning Wireless  5/20/09 5/26/09 100%
     Geer Bldg Automation  2/23/09 4/15/09 100%
     Geer Wireless  4/29/09 5/7/09 100%
     Sanders Bldg Automation  4/20/09 4/29/09 100%
     Sanders Wireless  5/12/09 5/20/09 100%
     Young Bldg Automation  5/05/09 5/13/09 100%
     Young Wireless  5/25/09 6/2/09 100%
     Cope - Bldg Automation  5/20/09 5/22/09 100%
     Cope Wireless  6/5/09 6/9/09 100%
     Benet - Bldg Automation  5/23/09 5/29/09 100%
     Benet Wireless  6/12/09 6/22/09 100%
     Mauldin - Bldg Automation  4/30/09 5/1/09 100%
     Mauldin Wireless  5/25/09 5/29/09 100%
     Lever - Bldg Automation  6/25/09 7/1/09 100%
     Lever Wireless  6/3/09 6/19/09 100%
     Byrnes - Bldg Automation  4/16/09 5/12/09 100%
     Byrnes Wireless  7/6/09 9/29/09 100%
     Barnett - Bldg Automation  4/15/09 4/20/09 100%
     Barnett Wireless  7/13/09 7/21/09 100%
     Smith - Bldg Automation  4/15/09 4/20/09 100%
     Smith Wireless  6/29/09 7/3/09 100%
     Johnstone Main and Annex - Bldg Auto.  7/8/09 7/16/09 100%
     Johnstone Main and Annex Wireless  7/23/09 11/25/09 50%
     Stadium Suites - Bldg Automation  7/13/09 7/17/09 100%
     Stadium Suites Wireless  7/20/09 9/1/09 100%
     Holmes Hall - Bldg Automation  7/27/09 7/31/09 100%
     Holmes Hall Wireless  7/31/09 10/9/09 100%
     Clemson House - Bldg Automation  8/4/09 8/10/09 100%
     Clemson House Wireless  8/31/09 9/9/09 100%
     McCabe Hall - Bldg Automation  8/18/09 9/18/09 100%
     McCabe Hall Wireless  8/10/09 10/9/09 100%
     Simpson North & South - Bldg Automation  9/2/09 9/8/09 100%
     Simpson North & South Wireless  8/28/09  11/25/09 100%
     Frat Quads  9/14/09         11/25/09       50%
     Project Close Activities  TBD      0%