Introduction to Nuclear Power
Ideas today about what to do about global warming
go in several different directions
Should we build new nuclear power plants?
- is it safe?
- do you have a logical site
to build it
- how does it affect the
community?
- environmental impact
- cost
- how did we get where we are?
Some of the scientists who had built the first
atomic bomb put their energy into the arms
race,
others saw the only way to make it all worthwhile to be to develop
peaceful
uses for atomic energy
- power was most promising, although a variety
of other
schemes were discussed
- the only interest of the Atomic Energy
Commission was
more bombs until about 1947, and even after that military needs were
first
priority. The AEC was worried about shortage of uranium.
However,
they did develop some reactor technology to produce plutonium, as at
the
Savannah River Plant.
- When the AEC first started planning
for nuclear power in 1948 they stressed breader reactors: produce
both
power and plutonium. Dec. 20, 1951, a fast breeder reactor became
the first reactor to generate significant power.
Lightbulbs
lit by first US reactor to supply electricity
- Meanwhile more practical reactor technology
was being
developed for the Navy. Admiral
Hyman Rickover was assigned by the Navy to Oak Ridge to study
reactors.
He became a true believer and in 1948 became head of a joint Navy-AEC
project
to develop a nuclear
submarine. He singlehandedly pushed the project through, and
the first
nuclear powered submarine was tested in prototype by Nov. 1952
first nuclear
submarine
A number of technologies were possible for nuclear
power
plants
- light water uranium reactors were picked for
the submarine
project because they took advantage of existing facilities for uranium
separation and had features (such as lack of exotic or dangerous
cooling
fluids) particularly useful for submarines
- Westinghouse, who was working on the Navy
project, proposed
using the same kind of reactor as a power plant--the first reactor for
commercial power generation was a 60 MW plant built by Westinghouse
with
AEC funding in Shippingport, Pennsylvania. It began operation in
1957, at an operating cost ten times the standard for electricity
generation
at the time. The best reactor for a submarine wasn't
necessarily the best for power plants.
- A number of experimental reactors were built,
including
liquid sodium breeder, boiling water, pressurized water. By the
end
of 1957 the AEC had 7 experimental reactors and 11 cooperative or
independent
industry projects.
Experimental
Breeder
Reactor
Period of slow development of commercial use
- The problems of developing nuclear power were
legal as
well as technological. In 1954 changes in the Atomic
Energy Act (in response to a
call by Eisenhower for peaceful uses in 1953) for the first time
allowed
private industry to owner reactors under AEC license and allowed AEC to
exchange technical data on nuclear power.
- Industry found that private insurance company
would only
come up with $60 million in insurance for commercial nuclear power
plants--not
nearly enough. The federal government stepped in with the 1957
Price-Anderson
Act, to allow the industry to get off the ground. The Price-Anderson
Act solved the insurance problem by releasing everyone involved in
building and operating a nuclear power plant from liability.
Damages
up to a specified amount would be paid from a pool first provided by
the
federal government and insurance companies and then funded by the
industry.
That meant that in the case of an accident all damages above the
limit--set
initially at $560 million--would not be compensated (unless the federal
goverment decided to provide more disaster aid).
- the AEC started subsidising private industry
construction
of reactors--which did not look economically feasible without
subsidy.
The Democrats and the scientists pushed the AEC to do more through the
50s, and the AEC by the 1960s did more promoting than regulating of
atomic
power
- But private industry was worried about whether
costs could
be brought low enough. At the time coal powered generation was
becoming
more efficient--the average cost of coal in 1964 was $5 per ton,
delivered,
so the lower fuel cost for nuclear power wasn't that big an advantage.
- worries about safety were also growing:
- An Experimental
Breeder Reactor in Idaho had a core meltdown in 1955. The
accident
was contained, but since EBR-1 was a breeder it could have turned into
a nuclear bomb (unlike conventional reactors).
- It led to the first important outside safety
study, WASH-740,
which estimated that a serious accident was no more likely than one
chance
in 100,000 per reactor year. However, it also estimated that a
serious
accident at a planned breeder reactor in Detroit would cause 3,400
deaths,
43,000 injuries, and $7 billion in property damage. (This was not
the most negative prediction--another scientific study of the same
breeder
accident scenario estimated 133,000 prompt deaths, 181,000 likely or
possible
long-term fatalities, and 245,000 massive somatic and genetic injuries).
- The reactor near Detroit was built and
quickly suffered
an accident whose seriousness is debated--one journalist wrote a book
titled We
Almost Lost Detroit with some fairly convincing evidence.
- progress was maintained by concentrating on
less ambitious
designs.
- By the end of 1962, the AEC had spent $1
billion and private
industry $500 million. The operating costs had dropped from 50
mills/kwh
or 10 mills/kwh, and was expected to drop quickly to 5 mills/kwh,
compared
to 4.1 to 6.2 for conventional power generation (they also predicted
that
costs would drop to 3.8 mills/kwh by 1980--in fact the cost in 1980 was
2.3 cents).
1971
Robinson plant near Hartsville SC
The period of enthusiasm
- Glen Seaborg, the chairman of the AEC,
predicted that
nuclear power would be the leading energy source in most of the world
by
the end of the century.
- the companies that built nuclear power plants
offered
fixed cost deals, probably the first six of which were priced below
cost.
Large numbers of orders were placed based on optomistic assumptions
about
how costs would continue to fall.
- Arab oil embargo of 1973 and the resulting
600% increase
in oil costs (between 1970 and 1973) gave a further boost, but even
with
low fuel and operations costs nuclear power was still not very
competitive
because of the very high and unpredictable construction costs (in which
interest rates played a key role, and the oil crisis led indirectly to
higher interest rates).
- By Dec. 1976 60 reactors
were completed
The beginning of the decline
- Only six new reactors were started between
1975 and 1980,
and there were 50 cancellations of previous orders and about 100
deferals.
Many of these were caused
by cost issues even before the accident at Three
Mile Island, March 28, 1979.
- public
perception was increasingly negative
- after Three Mile Island many new regulations
were issued,
increasing the cost of plants
Example Oconee
Nuclear Plant relicensing (first given
a 40 year licence in 1973-4)
- Oconee Nuclear was the
second nuclear power plant in the U.S. to be given an extension of its
operating license for an additional 20 years
- very little opposition
- zone map
- South
Carolina Energy Sources
Issues:
- Design life
- old technology
(eg. welds containing
copper and nickel)--cracks were discovered a few months after
relicensing
- Oconee already has over 1500
metric tons of radioactive waste on site
- financial: what are the
different kinds
of costs to be
considered?
- construction
costs (and how accurately
those can be predicted)
- operating and
maintenance costs
- changing
costs of alternative approaches
- regulatory
costs
- increasing costs due to public
pressure for increasing safety standards
- decommissioning
costs
New nuclear power plants
- There are currently 103
reactors in the U.S. generating about 20% of the nation's electricity
- six U.S. companies are
proposing to build new nuclear power plants
- on March 16, 2006 Duke Power proposed
two at a site in Cherokee
County next to where earlier
plans to build a nuclear power plant had been abandoned in the 1980s
- they have also considered
Oconee Nuclear for an additional reactor
Advantages:
- reduce global warming and
acid rain (the most economical fuel for electrical generation is coal)
- less dependent on foreign
oil
- all other alternative power
sources would be more expensive
- improved technology (failsafe
nuclear power plant design is possible)
Disadvantages
- accident risk is of large
accidents causing long term contamination
- potential terrorist targets
- nuclear waste problem is
not solved--Yucca
Mountain is supposed to open in 2017
- Yucca mountain has been
costing $500 million a year but when construction begins in ernest will
go over $1 billion a year
- strong political
opposition in Nevada