Prior to Award Notification
Extenuating circumstances may require a department or Principal Investigator to obtain a project number for a proposed project before OSP has received the formal award. Principal investigators may submit a Risk Project Approval form before the sponsor has given formal award notification. Due to the risk involved, the request must include the documentation and approvals as specified in the Division of Research policy for advance risk accounts.
There are some federal sponsors (DoD, NIH, NSF and USDA, as examples) and other non-federal sponsors that allow up to 90 days of pre-award costs (i.e. prior to the official start date) on projects where funding is imminent, but the award notice has not yet been processed. Though some federal agencies do permit 90-day pre-award costs, there are several that do not and almost all non-federal agencies do not permit pre-award expenses to be incurred before the official start date of the award. CPAC are to submit to the Director of GCA for setup and approval.